Baarmutha Park Toilets Replacement (completed 2023)

  • Project typeReplacement
  • Project value$100,000
  • Project scheduleCompleted
  • Completion Date28 April 2023
Baarmutha park toilets

We demolished the two existing toilet blocks and built a new accessible toilet block as well as a new footpath from the existing carpark to the new toilet block. The new toilet block includes an accessible toilet cubicle with a baby change table and an ambulant cubicle. 

Why was this project undertaken and how was it funded?

The Baarmutha Park Master Plan (undertaken in 2022) identified the need for the replacement of the existing public toilet block.  This project was being funded as part of our annual capital works program.  

Progress updates 

Thursday 6 April Update

The newly constructed accessible toilets are now open for use.

The electricity was connected on Thursday 6 April and while there are still some minor works that need to be completed, this will not impact the use of the facilities in the meantime.

 

Newly constructed accessible toilet facilities at Baarmutha Park

Friday 31 March Update

We've continued to make good progress on the construction of the new facility with the building slab and footpath poured this week.

Construction of the new building also began this morning.

 

Construction site showing facility construction in progress

Friday 3 March Update

Site works commenced in March 2023 with the demolition of the existing toilet block. Construction is expected to take approximately six weeks and be completed during April 2023.

 

 

Contact details

Matt Smith
1300 365 003