Beechworth Tennis Courts (completed 2022)

  • Project typeConstruction
  • Project value$1.085M
  • Project scheduleProject Complete
  • Completion Date01 May 2022
Beechworth Courts.png

About this project

The scope of this exciting project included four new courts that have cushioned acrylic surfacing constructed on a concrete base. It also provided for site preparation, court fencing, and competition standard low level LED lighting. The siting of the courts required re-alignment of the access road and provided for the construction of additional parking spaces.

The Victorian Government is provided a grant of $250,000 from the Local Sport Infrastructure 2020-21 – Community Facilities program, the Beechworth Lawn Tennis Club contributed $800,000 and $35,000 was allocated from Council's Capital Works 2021/22 Budget.

Why was this project being undertaken?

The Beechworth Tennis Club had been operating from its previous location for 83 years and are looking to encourage more participation for all ages.  The decision to build a brand new facility at Baarmutha Park will provide continuing economic and social benefits to our community.  It is hoped that this important development, will create increased participation in local tennis by providing a competition grade, compliant facility. The project will enhance the amenity of Baarmutha Park for the local community and the broader region to enjoy.

Project history

Construction was completed May 2022 with the facility handed back to the community for use.

May 2022 Update

The new Beechworth Tennis Courts have now been completed, the car park area is open and the courts are ready for use.

Any enquiries regarding access to the courts may be directed initially to the Beechworth Lawn Tennis Club at beechworthtennis@gmail.com

The club will soon have a new on line Book-a-Court system in place to facilitate bookings

An official opening is expected to be held later in the year.

 

March 2022 Update

The new courts are coming along brilliantly with the cushioned acrylic surface now complete. Construction of the car park is now underway.

 

Beechworth Courts.png

February 2022 Update

With construction of the new tennis courts now nearing completion, two representatives from Tennis Victoria were on site on Friday 18 February to inspect progress, together with the President of  Beechworth Tennis Club. After being closely involved in the planning for development of the new facility at Baarmutha Park, all were excited at the prospect of the courts being available soon for use.

One particularly exciting inclusion is the new Book-a-Court system. This is being installed to streamline the booking process for access to the courts for club members and visitors alike. The Book-a-Court system has been promoted and well supported by Tennis Victoria and it will continue to provide assistance to the local club in implementing it.

The LED lighting has now been erected and the cushioned acrylic surfacing is currently being laid. (Photo shows the rubber underlay being glued to the concrete base)

Pictured are;

Sam Condon (Tennis Victoria, Club Development Officer- North East), on the left

Andy Carr (President, Beechworth Tennis Club), middle

Justin Raiti (Tennis Victoria, Regional Tennis Manager – Country Eastern), right

 

Beechworth Tennis Courts Feb 22 Update.jpg  Beechworth Tennis Courts - Feb Update 2022.jpg

 

January 2022 Update

The concrete base for the courts was completed before Christmas and all fencing has now been finished. Works will begin in the first week of February to erect the lights and poles and complete the electrical connections. The laying of the cushioned acrylic surfacing for the four new courts will also proceed through February. This will be followed by the remaining civil works for the access road and car park, with a completion date extended to 31 March 2022.

Golf ball protection netting has been installed adjacent the first tee to protect car park users from any wayward golf balls. The type of netting chosen is also designed to be safe for birds.

Beechworth 13.jpg

November 2021 Update

Earthworks have progressed, with the new access road formed and the base foundation for the concrete slab for the tennis courts now being prepared.

Electrical conduits have also been installed in readiness for the new lighting. 

Beechworth Tennis Courts November.png

Update 26 November

The new tennis courts are beginning to take shape.

Foundation preparation has been completed and posts for the tennis court fence are being installed prior to laying of the concrete slab. The tennis court fence is being constructed with heavy duty posts to allow for the addition of windbreak screening mesh to the fence.

Photo below indicates progress to 18 November 2021.

Beechworth Tennis Courts - November Update 2.JPG

 

September 2021 Update

Site works commenced this week to prepare the site for construction of the new tennis Courts at Baarmutha Park. Security fencing has been erected around the site and the northern access road closed.

Beechworth Tennis Courts - Update 1.jpgBeechworth Tennis Courts 2 - Update 1.jpg

 

August 2021 Update

A detailed design has been finalised and a tender for construction has been advertised.

Tenders closed on 19 August 2021 and will be evaluated for Council’s consideration to award the contract.

A link to the tender information can be found here.

At its meeting of 31 August 2021 Council awarded a contract for construction of  the Beechworth Tennis Courts to iDwala Pty Ltd for the price of $1,031,439.60

Site works are expected to begin in September for completion by January 2022.

The northern entry to Baarmutha Park will be closed to traffic for the duration of the works. All access to facilities at Baarmutha Park should be via the main entry gate opposite Victoria Road.

 

 

 

 

 

Victorian-State-Government.jpg

Location

Balaclava Road Beechworth, Beechworth 3747  View Map