Footpath and Shared Pathways Program

Blanche Street - Footpath - June Update 1.png

The table below documents some of the footpath works we will undertake over the next year.

We will also undertake other projects on other paths and cycleways.

Footpaths

Location  Description

 

Budget
Path upgrade program - various locations

Proposed as per priority list:

  • Reid Street, Chiltern
  • Huon Kiewa Road, Tangambalanga
  • Stanley Street, Barnawartha
$56,891
Peach Drive Construction of 250m of concrete shared path, linking between the primary school, and the rail trail. $88,075
Harper Avenue Beechworth 130m of new footpath from Albert Road to the Skate Park. $60,000
Various locations Priority renewals of various sections of footpaths across the Shire based on asset condition $85,686
Beechworth footpath renewal and risk reduction Safety works at identified priority locations $4,500
$293,261